Operatives to commence cleaning of the ceiling. Cleaning to be carried out systematically ensuring that each area of ceiling is cleaned and any excess solution wiped off immediately from surrounding surfaces.
11  Operatives to pay extra care and attention where water or solution drips on to floors or may leak to basement areas below.
12  Operatives to rinse off cleaned section using clean water before progressing to next section.
13  On completing cleaning operations, operatives to descend from access equipment and carefully remove cleaning equipment back to floor level, observing safe manual handling techniques.
14  Operatives to carry out a visual check of the ceiling from ground level to ensure all areas have been cleaned as per the specification.
15  Operatives to dispose of all waste chemicals and materials on site and remove all cleaning equipment, chemicals and signage to company vehicle.
16  Operatives are not to leave the site until authorised by Supervisor.